Parcel: 11520198A

Inspection Status: Partial Pass

Inspection History

Permit Number - TD-DEV-0623-00272

Inspection Description -

Inspection Status - Partial Pass

Date Description Inspector Results Comments
01/15/2025 Partial Pass Contractor needs to remove some of the sidewalk that is noncompliant and build it to per plan. The sidewalk on the west side of the project has not been started. Contractors waiting for the reclaimed water to be installed on that west side.
09/05/2024 Partial Pass 10x200 sidewalk good to pour north side of the park
09/11/2024 Partial Pass Contractor formed up for some sidewalk using number three bar at the north west ballpark area 8’ x 200
09/17/2024 Partial Pass Contractor pouring sidewalk 10’ x 200 lineal foot everything looks good at this time
09/18/2024 Partial Pass Contract pouring more sidewalk 10 x 200 lineal feet
09/20/2024 Partial Pass Looked T approximately 120 feet of 10 foot of sidewalk poured today. The Contractor will provide the photographs of the areas poured today via email on Monday
09/24/2024 Partial Pass it ok for the contractor to pour 10x200 lf. of sidewalk.on the south of the ball field.
09/25/2024 Partial Pass Contractor point sidewalk 10 x 200 using number three rebar 18 in centers at Ramada Circle area
09/27/2024 Partial Pass inspected and highlighted sections of sidewalk as noted on the plans inside the construction trailer for this date
10/04/2024 Partial Pass Sidewalk approved as noted for the site. Also look at the trash enclosure for the final lift of grout.
10/14/2024 Partial Pass As noted on the plans in the Contractors trailer for this date.
Partial passed Approved at this time pending photographs of additional Adobe Blocks being added for additional support of the rebar mat. Another Inspection is scheduled for Matin to verify the work is as needed in the morning.
10/16/2024 Partial Pass Contractor point sidewalk just west of the ballpark right next to the concession building 10’ x 100’. There’s an area there that is an irrigation leak and it flooded the area so they can’t pour concrete there.
10/30/2024 Partial Pass Contractor needs to call in for inspections on the sidewalk that’s being formed on the north west side of the park
10/31/2024 Partial Pass Contractors good to pour the sidewalk on the west end of the park by the Ramadas
11/05/2024 Partial Pass Contractors pouring sidewalks between the baseball field. 155’ x 10’.
11/07/2024 Partial Pass Contractor continues sidewalk on the north side by the baseball field 10 x 100’
11/14/2024 Partial Pass Contractors good to pour the floor and the apron for the trash enclosure. And good to porch sidewalk 10’ x 200 with a 18 inch toe.
11/18/2024 Partial Pass poured the sidewalk on the south end of the park by the playground
11/19/2024 Passed sidewalk 10x100 west of the playgrounds