Parcel: 134162140


Addresses:

7101 E 22ND ST


Inspection Status: Not Ready

Inspection History: For trash and recycling enclosures

Permit Number - TD-DEV-0525-00137

Inspection Description - For trash and recycling enclosures

Inspection Status - Not Ready

Date Description Inspector Results Comments
09/09/2025 For trash and recycling enclosures Not Ready
09/10/2025 For trash and recycling enclosures Partial Pass 9/10/25
Footer for RE Wall. Rebar correct. Footer Dimensions correct for TSMR. Bollards are not dug yet but spacing is correct and they will be dug and inspected before slab is poured with mat. Contractor plans on building wall all the way up and installing Bond beam at top and weep holes bottom and will call in inspection before grouting. Ok to pour RE footer.
10/01/2025 For trash and recycling enclosures Partial Pass 10/1/25 pre grout-
One vert at wall end section is missing and center column is not built completely, not all grout weep holes are punched. Contractor will provide pictures showing correct column with correct reinforcement and correctweep holes at slab for grout. Otherwise reinforcing and bond beam at top correct, walls are ready. OK to grout walls up to Bond beam pending pictures showing corrections above. Send pictures of grout through weep holes when grouting.

Request inspections for bollards in refuse enclosure and floor before they are poured.
10/08/2025 For trash and recycling enclosures Partial Pass 10/8/25
Forms and Bollard footers and placement correct. Slopes correct. Contractor will submit compaction test of AB to portal at RE slab. Completed and correct rebar mat pictures and compaction field report will be sent to me before pour. Pending these and acceptable weather conditions for concrete placement, okay to pour RE floor and apron.