Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you can not find what you are looking for please submit a records request.
Inspection History Details
Inspection Status: Not Ready
Inspection History
Permit Number - TD-DEV-0524-00161
Inspection Description -
Inspection Status - Not Ready
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 07/14/2025 | Not Ready | Side walks cannot be poured as is. Drainage pipe needs to be removed and scuppers will need to be used in place. Rebar touching dirt is not allowed. 3" from bottom of rebar touching dirt and 2" everywhere else, such as space between rebar and forms and rebar and sides. All sections were typically set. | ||
| 07/16/2025 | Partial Pass | The engineer on record will have to approve of the trench drains used as these look like a residential type drain. Everything can be poured that has been formed except the area in question where the drains are located. | ||
| 07/30/2025 | Partial Pass | 07/30/25, on the front of the building, 2 automotive ramps into the building, the ramp section for ADA minus the drain areas, the ramp on the far south of the building are good to pour. | ||
| 08/05/2025 | Partial Pass | Do not pour the roof drain areas until an engineer or architect on record approves with a stamped letter. | ||
| 09/30/2025 | Passed |