Inspection Status: Partial Pass

Inspection History: For trash and recycling enclosures

Permit Number - TD-DEV-0523-00250

Inspection Description - For trash and recycling enclosures

Inspection Status - Partial Pass

Date Description Inspector Results Comments
09/02/2025 For trash and recycling enclosures Partial Pass Trash enclosure (both) footing excavation has correct reinforcement and dimensions, okay to pour.
09/16/2025 For trash and recycling enclosures Partial Pass 9/16/25
Slabs okay to pour. Slope is correct. Compaction test done. Reinforcing correct. Correct to survey.

9/16/25
Horizontal reinforcing needed 16” oc in wall. Put it in and build the wall up another 2 courses before pre grout inspection on 1st lift.
09/25/2025 For trash and recycling enclosures Partial Pass 9/25/25
Ok to grout walls. Call us back out for pregrout inspection when done w with second lift. Grout all cells Vibrate all grout.
10/10/2025 For trash and recycling enclosures Partial Pass 10/10/25
Bond beam at top of wall correct for both enclosures. Okay to grout second lift-vibrate all grout.