Inspection Status: Partial Pass

Inspection History

Permit Number - TD-DEV-0523-00250

Inspection Description -

Inspection Status - Partial Pass

Date Description Inspector Results Comments
09/16/2025 Partial Pass 9/16/25 Footer goes along west side of site from south of the driveway continuing north to refuse enclosures and then to the north east corner and turns the corner over to the building. Footer correct to building plans. Campaction reinforcing and dimensions are correct. This section of wall footer is OK to pour.
Build wall to plan in two lifts and call us out for a pre-grout inspection when done with first lift. Also call us out to look at any other site wall footers.