Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you cannot find what you are looking for please submit a records request.

Inspection Status: Not Ready

Inspection History: For trash and recycling enclosures

Date Description Inspector Results Comments
03/24/2026 For trash and recycling enclosures Not Ready 3/24/26
Footer for wall
Stakes supporting/wired to hors are not isolated well enough. Dobies and or suspending
From above is better. Not all rebar is 3" clear of the dirt.
03/26/2026 For trash and recycling enclosures Partial Pass 3/26/26
Wall Footer reinforcing and Post footers are correct. Okay to pour footer.
Build wall using 9 GA. horizontal reinforcemeint @ 16" OC. In 2 lifts and schedule Refuse Enclosure inspection for pre grout inspection before grouting both lifts or you may build to the top bond beam and schedule pre grout inspection before grouting. Cut Weep knockouts at bottom of all verts for this option.
Schedule inspection/s for bollards and floor reinforcing and placement.
04/10/2026 For trash and recycling enclosures Partial Pass Weep holes cut- wall topped out. I witnessed the cells were clean. Mason will cover weep holes and wants to use vibrator. Bond beam in place at top correct. Vibrate all grout. Pictures illustrating vibration to be sent.
06/02/2026 For trash and recycling enclosures Passed PCCP floor to plan 8”+