Inspection History Details
Inspection Status: Not Ready
Inspection History: For trash and recycling enclosures
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 03/24/2026 | For trash and recycling enclosures | Not Ready | 3/24/26 Footer for wall Stakes supporting/wired to hors are not isolated well enough. Dobies and or suspending From above is better. Not all rebar is 3" clear of the dirt. |
|
| 03/26/2026 | For trash and recycling enclosures | Partial Pass | 3/26/26 Wall Footer reinforcing and Post footers are correct. Okay to pour footer. Build wall using 9 GA. horizontal reinforcemeint @ 16" OC. In 2 lifts and schedule Refuse Enclosure inspection for pre grout inspection before grouting both lifts or you may build to the top bond beam and schedule pre grout inspection before grouting. Cut Weep knockouts at bottom of all verts for this option. Schedule inspection/s for bollards and floor reinforcing and placement. |
|
| 04/10/2026 | For trash and recycling enclosures | Partial Pass | Weep holes cut- wall topped out. I witnessed the cells were clean. Mason will cover weep holes and wants to use vibrator. Bond beam in place at top correct. Vibrate all grout. Pictures illustrating vibration to be sent. | |
| 06/02/2026 | For trash and recycling enclosures | Passed | PCCP floor to plan 8”+ |