Inspection History Details
Inspection Status: Passed
Inspection History
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 03/03/2026 | Passed | 3/3/26 Forms for 6" slab all below less than 2%. Rebar and Turn Down correct. Welded wire in place and dowels placed in adjacent footers. Dobies were used for clearance of reinforcing. Okay to pour slab |
||
| 04/14/2026 | Canceled | |||
| 06/02/2026 | Partial Pass | Sidewalk consultation. Discussed how to make SD PAG 207 type 2 curbs (per plan) work for the site. Currently slope is over 8.33 percent at west corner of building. There will be an additional landing to connect perpendicular ramps at corner and then down again to asphalt. Also a sidewalk scupper needs to be incorporated here PAG 204 type 1 would be best at landing of door. Also west sidewalk in Landscaping will be PAG 200 that jogs and curves to avoid existing trees etc. Sleeves for irrigation will be in place. | ||
| 07/16/2026 | Passed | South curb ramp at sidewalk along I-10 does not comply. Over 8.33% |