Inspection History Details
Inspection Status: Partial Pass
Inspection History
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 04/07/2026 | Partial Pass | Some storm drain work has been completed but is still visible for inspection. 30" RCP at northwest corner is already in place: bedding looks correct, backfill appears accurate, pipe material is correct, slope & elevations are good. 42" RCP extension of existing at Mideast is in place: bedding looks correct, backfill appears accurate, pipe material is correct, slope & elevations are good. Schedule an inspection for the rebar in the spillway prior to pouring concrete. 24" RCP at Midwest is not in place yet: schedule an inspection for the trench and bedding material, and prior to backfill for pipe verification. 66" existing RCP on north side: rock splash pad to be installed to prevent erosion of channel floor. |
||
| 04/09/2026 | Partial Pass | Headwall on west border (10th ave) for 42" RCP outlet: floor and toe down are formed with appropriate dimensions and reinforcement per ADOT SD 6.30-3. Okay to pour floor and toe down. |