| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 01/02/2026 | Grading Progress ENGR | Not Ready | Will reschedule for Monday, 01-05-26, Contractor is going to roll balance of west parking area on 01-03-26 | |
| 01/05/2026 | Grading Progress ENGR | Partial Pass | ||
| 01/07/2026 | Grading Progress ENGR | Partial Pass | Contractors good to start placing AB on the west parking lot area | |
| 01/16/2026 | Grading Progress ENGR | Not Ready | 1/16/25 Grading progress/ Paving inspection for AB on west corner of Site. From west side over to the large islands where the rectangular area meets the rest of the area. AB for this area is not completely ready for Asphalt. Will inspect again next Tuesday mid morning. |
|
| 01/20/2026 | Grading Progress ENGR | Partial Pass | Contractor, good to backfill the reducer at the catch basin on the southwest corner of the project. It went from 24 to 36 inch storm drain. | |
| 01/21/2026 | Grading Progress ENGR | Partial Pass | Contractor is good to pour the curbs and gutter in front of the building on the north side | |
| 01/22/2026 | Grading Progress ENGR | Partial Pass | Contractor is good to start placing a B in section B | |
| 01/30/2026 | Grading Progress ENGR | Partial Pass | 1/30/26 Subgrade inspection for outdoor showroom area. Rectangular area to east of building that all slopes toward catch basin midway at west side of area, just east of loading dock. This catch basin has not been installed yet. Density testing complies. Grade is even and sloped correctly into catch basin, hubs in place and good. OK to place AB for 3" over 4" light duty asphalt |
|
| 02/03/2026 | Grading Progress ENGR | Not Ready | I need to come back about 2 o’clock and address the pumping areas around the storm drain trench it’s all been pumping I returned about 2 o’clock this afternoon to see if they had fixed the pumping area. And they haven’t. They’ll probably call in for another inspection tomorrow or Thursday. |
|
| 12/02/2025 | Grading Progress ENGR | Partial Pass | Contractors good to place the AB at the loading dock area | |
| 12/11/2025 | Grading Progress ENGR | Partial Pass | Contractor grading for curb in the west parking lot area islands 12 different islands contractor formed up all good they can pour concrete | |
| 12/17/2025 | Grading Progress ENGR | Partial Pass | Contractors good to pour for the islands on the west parking lot of the project | |
| 12/22/2025 | Grading Progress ENGR | Partial Pass | Contractors good to pour the islands in the parking lot area, West End of the building | |
| 12/29/2025 | Grading Progress ENGR | Partial Pass | Contract is good to pour the little islands in the parking lot on the west end of the building |