Inspection Status: Partial Pass

Inspection History

Permit Number - TD-DEV-0424-00140

Inspection Description -

Inspection Status - Partial Pass

Date Description Inspector Results Comments
09/26/2025 Partial Pass 18" storm drain, 60' from T1 to T2: pipe and catch-basins are correct, depth and elevations are correct. Okay to backfill.
09/30/2025 Partial Pass Contract is good to backfill 124 lineal feet of 24 inch pipe. Northwest area.
10/03/2025 Partial Pass Okay to backfill HDPE runs at catch basin
10/06/2025 Partial Pass Contractor, good to backfill the 18 inch HDPE 134 lineal feet and the other HDPE 18 inch 100 foot
10/08/2025 Partial Pass Contractor is good to backfill the 12 inch HDPE pipe going into the building approximately 100 lineal feet
10/10/2025 Partial Pass okay to backfill
10/21/2025 Partial Pass Contractors good to backfill the 12 inch HDPE pipe and the 24 inch. There is 180 lineal feet of the 12 inch and 100 feet of the 24 inch and two laterals at 60 feet each of 12 inch.
10/24/2025 Partial Pass Okay to backfill SD run CB2-CB3
10/29/2025 Partial Pass contractors good to install the collar on the south west corner of the project. Contractor also has another one to install a collar on the north east quadrant contractor give us a call before back filling
11/05/2025 Partial Pass Contractors good to backfill the storm drain one of them at the north west corner contractor tap into the existing catch basin. The other one is at the north east corner tap into the existing catch base there also are good backfill
11/19/2025 Partial Pass shading verified via photo. okay to backfill
11/28/2025 Not Ready Additional bedding and shading required prior to backfill. Send photos or reschedule prior to backfill.
12/03/2025 Partial Pass Contractors good to backfill the HDPE pipe for the island in the parking lot area