| 10/31/2025 |
ENGR - Drainage Structures |
|
Partial Pass |
Discussed Catch Basin construction where plan detail is missing at NW corner of site. will reinspect prior to pouring the floor. |
| 11/06/2025 |
ENGR - Drainage Structures |
|
Partial Pass |
Okay to pour invert slab of CIP Catch Basin at NW corner of the site. |
| 11/10/2025 |
ENGR - Drainage Structures |
|
Partial Pass |
Okay to button up forms on E2. call for inspection prior to pouring concrete. |