Inspection History Details
Inspection Status: Partial Pass
Inspection History: PDSD Engineering Division Pre-Construction SITE
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 05/27/2026 | PDSD Engineering Division Pre-Construction SITE | Partial Pass | 5/27/26 - Discussed location of accessible parking and entrance. Okay to have parking and entrance at East side. ADA parking dimensions are 8-0 space with 5-0 aisle. Storm water needs to be conveyed away from the building without being discharged over pedestrian routes. *Actual Pre-Construction Meeting needs to be scheduled for this Development Package. |
|
| 09/11/2026 | PDSD Engineering Division Pre-Construction SITE | Passed | Outstanding conditions need to be satisfied prior to final. Build the site per DP plans or submit As-builts showing differences from accepted plans need on the DP Permit. |