Inspection Status: Partial Pass

Inspection History: For trash and recycling enclosures

Date Description Inspector Results Comments
01/09/2026 For trash and recycling enclosures Partial Pass 01/09/26
Wall built to 6' -Reinforcement correct. At end of walls and columns contractor is grouting embed plates from footer to top, just in the first cells that plates are embedded. the rest of wall has 1st lift grouted already. Rebar here will be wet set all the way down. Weep holes punched at bottom of these cells and contractor will send pictures of grout coming out of weep holes for each Refuse Enclosure. OK to grout second lift and embed plates. Vibrate all grout in reinforced cells.

Engineer of record to provide as-built changes to sidewalks and PCCP parking spaces and drives in front of building roll up doors, as well as any other changes to approved plans. Please copy rfi’s and changes to plans to my email.
02/03/2026 For trash and recycling enclosures Partial Pass 2/3/26
Bollard placement is correct okay to pour footers
02/06/2026 For trash and recycling enclosures Partial Pass 2/6/26
Ok to grout wall to the top of wall. Vibrate all grout. Reinforcing correct. Okay to finish wall after grouting
02/11/2026 For trash and recycling enclosures Partial Pass 12/11/26
Rebar is correct, forms correct. Expansion material in place
Okay to pour floor.
04/09/2026 For trash and recycling enclosures Passed
11/13/2025 For trash and recycling enclosures Partial Pass 11/13/25
Reinforcing and dimensions correct for a double TSM refuse enclosure footer. Send picture of expansion joint in the middle of the back wall with number four verts on each side and 3" clearance at wall ends cleaned up of loose dirt. Okay to pour footer with pictures.
Build wall to 4' and request pre grout inspection when ready. Request inspections when bollard footers and floor rebar mat Are ready.
12/24/2025 For trash and recycling enclosures Partial Pass contractors good to grout the first 4 feet of the trash enclosures