Inspection Status: Passed
Inspection History: ENGR - Drainage Structures
| Date |
Description |
Inspector |
Results |
Comments |
| 01/03/2025 |
ENGR - Drainage Structures |
|
Passed |
|
| 08/27/2024 |
ENGR - Drainage Structures |
|
Partial Pass |
Contractor excavated for the footer for the trash enclosure it’s good |
| 10/12/2023 |
ENGR - Drainage Structures |
|
Not Ready |
there will be two trash enclosures constructed. Per detail 801. |
| 11/25/2024 |
ENGR - Drainage Structures |
|
Not Ready |
Basins are not completed yet contractors still working on them |
| 12/13/2024 |
ENGR - Drainage Structures |
|
Re-inspection required |
Depth of Light pole holes insufficient and side clearance insufficient. No seismic tie hooks on horizontal rebar. Cages must be redone to include 135 deg. tie hooks |
| 12/19/2024 |
ENGR - Drainage Structures |
|
Partial Pass |
15 light poles footings inspected -5 failed. Must reinspect before pour. |
| 12/20/2023 |
ENGR - Drainage Structures |
|
Partial Pass |
On site with Joseph from Canyon. Basic rough, grading and demo cleanup in progress. |
| 12/20/2024 |
ENGR - Drainage Structures |
|
Re-inspection required |
I went to site to inspect 5 light poles that had failed yesterday. All 5 still did not pass today. They did not meet the minimum depth below ground surface. |
| 12/27/2024 |
ENGR - Drainage Structures |
|
Not Ready |
|