Inspection History Details
Inspection Status: Requested
Inspection History
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| Requested | ||||
| 05/14/2026 | Partial Pass | okay to pour the footer on the east side for site wall.. They can also pour for the footer for the trash enclosure. And the footer for the site wall on the west side. | ||
| 07/30/2026 | Partial Pass | Retaining wall footing on East border wrapping around to South border: dimensions, reinforcement, and locations are correct. Okay to pour footing. | ||
| 08/04/2026 | Partial Pass | Wall on West border: Footing excavation and reinforcement are good. Okay to pour. | ||
| 08/25/2026 | Partial Pass | Lower lift on West wall: horizontal reinforcement is in place, vertical reinforcement is #5 bars 24-OC for up to 2' retaining. Okay to grout 1st lift. | ||
| 08/28/2026 | Not Ready | 8/28/27 South wall not ready. Verts and Bond beam are not in place. Do not grout until approved. Schedule inspection for Monday. |