Inspection History Details
Inspection Status: Partial Pass
Inspection History
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 05/14/2026 | Partial Pass | okay to pour the footer on the east side for site wall.. They can also pour for the footer for the trash enclosure. And the footer for the site wall on the west side. | ||
| 07/30/2026 | Partial Pass | Retaining wall footing on East border wrapping around to South border: dimensions, reinforcement, and locations are correct. Okay to pour footing. | ||
| 08/04/2026 | Partial Pass | Wall on West border: Footing excavation and reinforcement are good. Okay to pour. | ||
| 08/25/2026 | Partial Pass | Lower lift on West wall: horizontal reinforcement is in place, vertical reinforcement is #5 bars 24-OC for up to 2' retaining. Okay to grout 1st lift. | ||
| 08/28/2026 | Not Ready | 8/28/27 South wall not ready. Verts and Bond beam are not in place. Do not grout until approved. Schedule inspection for Monday. |
||
| 08/31/2026 | Partial Pass | South half of East wall, ready for grout for first lift of wall on top of retaining wall. Southeast wall OK to grout up to bond beam pending good pictures. Showing completed bond beam. | ||
| 09/03/2026 | Partial Pass | East wall first lift above retention wall OK for grout weather permitting. As wall runs south it transitions to second lift of wall. This wall section to the SE corner is complete to top with bond beam. OK to grout second lift with bond beam. | ||
| 09/15/2026 | Partial Pass | -Pre grout inspection of 1st lift of screen wall on west side. Okay to grout. Vibrate all grout. Schedule this inspection again when wall is built to top course with bond beam. | ||
| 09/17/2026 | Passed |