Inspection Status: Partial Pass
Inspection History
| Date |
Description |
Inspector |
Results |
Comments |
| 06/04/2026 |
|
|
Partial Pass |
contractor go ahead and pour the curb in front of the building .and the curb for the entrance |
| 06/12/2026 |
|
|
Partial Pass |
Okay to pour curb along south edge of building. |
| 06/18/2026 |
|
|
Partial Pass |
ok to pour the curb on the west side and south side. |
| 07/07/2026 |
|
|
Partial Pass |
Sidewalk forms along North side of building: sub-grade, slopes, & dimensions look okay. Good to pour. |
| 08/19/2026 |
|
|
Partial Pass |
Refuse enclosure subgrade is good. Instructed superintendent to use #4 rebar for the slab and 'Refuse Enclosure' for the inspections. Next inspection will be slab reinforcement prior to pour. |
| 08/27/2026 |
|
|
Partial Pass |
Valley gutter forms are set up correct. Slope, depth, dimensions, and compaction are good. Okay to pour. |
| 09/11/2026 |
|
|
Not Ready |
Fix for sidewalk scuppers not ready. 4" depth down and to sides of scupper walls needed for pour. Reschedule this when ready and also pre grout wall inspections for the west wall. |
| 09/17/2026 |
|
|
Partial Pass |
Scuppers are fixed. |