Inspection History Details
Inspection Status: Partial Pass
Inspection History
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 04/29/2026 | Partial Pass | Curb ramp on south side of store OK to pour. There will need to be another small curb ramp with 2 inch rise at north east corner of building. There's a crosswalk there and the curb is not flush with asphalt. There is plenty of room for a small 2.5'-3' run with no more than 8.3% running slope, with two small wings on either side. I went over striping layout for parking. Bollards are placed correct. | ||
| 05/06/2026 | Partial Pass | 5/6/26 Ramp, handrail and Curb ramp at SW corner of building comply. |
||
| 05/14/2026 | Partial Pass | Okay to Pour small curb ramp at NE corner of building. | ||
| 05/29/2026 | Passed |