Inspection History Details
Inspection Status: Partial Pass
Inspection History
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 07/29/2026 | Partial Pass | Trenching for irrigation main line on south side of park, approximately 120 lf from Florence is good. Trenching for underground electrical on south side of park, approximately 120 lf from Florence is good. |
||
| 08/04/2026 | Not Ready | 3" mainline needs to be bedded with fine sand or clean soil 3" below and above pipe as shown on Irrigation Trenching detail 38 page 16 on DP. There are areas in trench where 24" of clearance will not be met with this bedding. Bed the mainline per detail and reschedule inspection when ready. | ||
| 08/06/2026 | Partial Pass | South section of 3" sch 40 PVC Irrigation mainline is bedded at correct depth per detail 38 sheet 16. Contractor is now placing thrust blocks per plan, detail 43, sheet 17. Schedule inspection when thrust blocks ready. | ||
| 08/07/2026 | Partial Pass | South half of layout-3" pvc mainline thrust blocks are correct to detail 43 sheet 17 and trenching detail. Okay finish shading and place backfill in areas as needed. Continue scheduling these inspections for second half of mainline. Pressure test with park PM when mainline finished with all valves. | ||
| Scheduled |