Inspection Status: Partial Pass
Inspection History
| Date |
Description |
Inspector |
Results |
Comments |
| 05/23/2025 |
|
|
Partial Pass |
Buildings B & C flat work at interior patios. Maintain a 2" separation from dirt on a 4" slab using #3 rebar. Insure that size of turndown is suitable for the weight of the staircases. |
| 08/19/2025 |
|
|
Partial Pass |
08/19/25, leading edge of the atrium sidewalks going into units on building 4, lower level. |
| 09/18/2025 |
|
|
Partial Pass |
Contractors pouring curb on the south end of the buildings good pour |
| 10/08/2025 |
|
|
Failed |
Sidewalk area needs to be compacted in front of building C |
| 11/03/2025 |
|
|
Partial Pass |
Contract is good for 200 lineal feet of valley gutter |