Inspection Status: Partial Pass
Inspection History: ENGR - Drainage Structures
| Date |
Description |
Inspector |
Results |
Comments |
| 01/11/2024 |
ENGR - Drainage Structures |
|
Partial Pass |
contractor called in for the wrong inspection. He needed inspections for the wattles. Contractor will call in for rebar inspection for tomorrow for trash enclosures. |
| 01/18/2024 |
ENGR - Drainage Structures |
|
Not Ready |
Contractor will reschedule for Monday or Tuesday. |
| 01/30/2024 |
ENGR - Drainage Structures |
|
Not Ready |
Contractor called me, and he informed me that the footer for the trash enclosure is not ready to be inspected |
| 01/31/2024 |
ENGR - Drainage Structures |
|
Not Ready |
Stop by to inspect the rebar for the footer for trash enclosure, not ready contractor will reschedule for tomorrow |
| 02/01/2024 |
ENGR - Drainage Structures |
|
Partial Pass |
contractors good for the footer for the trash enclosure. He has two number four bars running vertical and spacing horizontally number for bars every 32 inches at the end. He has double number four bars and in the corners to number four bars. |
| 02/20/2024 |
ENGR - Drainage Structures |
|
Partial Pass |
Contractors good to grout for the trash enclosure at 6 foot and the bond beam in |
| 04/26/2024 |
ENGR - Drainage Structures |
|
Partial Pass |
Trash enclosure slab. Jason with MW Morrissey. |
| 07/03/2024 |
ENGR - Drainage Structures |
|
Passed |
|