Permit: TD-DEV-0123-00096

Parcel: 13608477H

Inspection Status: Partial Pass

Inspection History: ENGR - Drainage Structures

Date Description Inspector Results Comments
01/11/2024 ENGR - Drainage Structures Partial Pass contractor called in for the wrong inspection. He needed inspections for the wattles. Contractor will call in for rebar inspection for tomorrow for trash enclosures.
01/18/2024 ENGR - Drainage Structures Not Ready Contractor will reschedule for Monday or Tuesday.
01/30/2024 ENGR - Drainage Structures Not Ready Contractor called me, and he informed me that the footer for the trash enclosure is not ready to be inspected
01/31/2024 ENGR - Drainage Structures Not Ready Stop by to inspect the rebar for the footer for trash enclosure, not ready contractor will reschedule for tomorrow
02/01/2024 ENGR - Drainage Structures Partial Pass contractors good for the footer for the trash enclosure. He has two number four bars running vertical and spacing horizontally number for bars every 32 inches at the end. He has double number four bars and in the corners to number four bars.
02/20/2024 ENGR - Drainage Structures Partial Pass Contractors good to grout for the trash enclosure at 6 foot and the bond beam in
04/26/2024 ENGR - Drainage Structures Partial Pass Trash enclosure slab. Jason with MW Morrissey.
07/03/2024 ENGR - Drainage Structures Passed