Inspection Status: Not Ready
Inspection History: COT - LCEL - Electrical Underground
| Date |
Description |
Inspector |
Results |
Comments |
| 04/23/2026 |
COT - LCEL - Electrical Underground |
|
Not Ready |
4-23-26: not ready-contractor will reschedule. |
| 04/24/2026 |
COT - LCEL - Electrical Underground |
|
Partial Pass |
4-24-26: conduits located on north side of site. Trench depth at 3' for 2-4" schedule 40 conduits for ct can, 1-2" for temp power. 2' trench depth for 2-4" schedule 40 conduits for cox cable/ irrigation & 1 -2 1/2" for data. Okay to backfill approximately 50' of trenches using shading materials. |
| 05/06/2026 |
COT - LCEL - Electrical Underground |
|
Partial Pass |
5/6/2026 Partial pass. Two 4” schedule 40 at 36” depth. From center pole to building. Okay to backfill progress areas. Shading required. |