Inspection Status: Re-inspection required
Inspection History: COT - LCEL - Electrical Progress
| Date |
Description |
Inspector |
Results |
Comments |
| 03/21/2025 |
COT - LCEL - Electrical Progress |
|
Re-inspection required |
3/21/25: called Roman Nunez, phone number: (520) 331-7340 no answer. Arrived on site waited 10min, no answer no access |
|
COT - LCEL - Electrical Progress |
|
Re-inspection required |
7-21-25: not ready for finals. Contractor will work on TEP requirements, label breaker at panel, install address identification label and reschedule when ready. |
| 08/01/2025 |
COT - LCEL - Electrical Progress |
|
Not Ready |
|
| 08/22/2025 |
COT - LCEL - Electrical Progress |
|
Partial Pass |
8-22-25: Verified trench depth for a Schedule 80-3" electrical feeder conduit. Okay to backfill approximately 60' of open trench. |