Inspection History Details
Inspection Status: Passed
Inspection History: COT - LCEL - Electrical Underground
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 01/27/2026 | COT - LCEL - Electrical Underground | Passed | ||
| 09/08/2025 | COT - LCEL - Electrical Underground | Partial Pass | Partial pass. 1” schedule 40 at 26” of depth running to light poles west end light poles of parking lot. Total of 5. P1 and P2. Okay to backfill progress areas. 9/8/2025 | |
| 09/16/2025 | COT - LCEL - Electrical Underground | Partial Pass | Clinic secondaries under road. | |
| 09/30/2025 | COT - LCEL - Electrical Underground | Partial Pass | X6 1 1/4” schedule 40 feeding EV charging stations heading to new switch gear location. X5 1 1/4” separate trench heading towards new switch gear location. X1 1” is for future monument sign. East end of parking lot. Behind curb. All Stub up for future Ev chargers. Total of 11. Okay to backfill progress areas. 9/30/2025 |