Inspection History Details
Inspection Status: Partial Pass
Inspection History: COT - LCEL - Electrical Underground
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 08/06/2026 | COT - LCEL - Electrical Underground | Partial Pass | 08/06/2026 Partial pass. Verified grounding ring and rods at tower foundation and transformer. Okay to proceed in progress areas. |
|
| 08/13/2026 | COT - LCEL - Electrical Underground | Partial Pass | 2 1/2” schedule 40 from disconnect ran to future Verizon 200a outdoor intergrated load center. From intergrated load center to new composite pad underground conduit verified per plan. Okay to backfill progress areas. Shading required. 8/13/2026 | |
| 09/30/2026 | COT - LCEL - Electrical Underground | Partial Pass | 09/30/2026 Partial pass. Verified Ufer and grounding rods for meter and disconnect bank near CMU wall. Okay to backfill progress areas. |