Inspection Status: Partial Pass

Inspection History: COT - LCPL - Sewer 

Permit Number - TC-UTL-0425-00026

Inspection Description - COT - LCPL - Sewer 

Inspection Status - Partial Pass

Date Description Inspector Results Comments
10/24/2025 COT - LCPL - Sewer  Partial Pass 10-24-25: verified trench depth of over 5' to grade on a 6" SDR35 pvc sewer line located at the southwest quad of site. Sewer pipe verified under test-okay to backfill approximately 90' of open trench with shading materials.
10/28/2025 COT - LCPL - Sewer  Partial Pass 10-28-25: verified approximately 195' of " SDR35 PVC pipe located on the west side of site that runs south to north under test. Okay to backfill progress areas with shading materials.
10/31/2025 COT - LCPL - Sewer  Partial Pass 10-31-25: verified approximately 120' of 6” SDR 35 PVC Sewer line under test at the west side of site. Okay to backfill trench using shading materials.
11/04/2025 COT - LCPL - Sewer  Partial Pass Main sewer line (6”) at Northwest portion of building; approximately 195’. Ok to back fill progress areas.
11/07/2025 COT - LCPL - Sewer  Partial Pass Sewer line at Northwest corner of building at Northeast area of hotel; approximately 35’, Ok to cover progress area.
11/12/2025 COT - LCPL - Sewer  Partial Pass Six inch sewer line at West area North of hotel at approximately 75’ to new man hole. Additional sewer line at Northwest building area to central area North at 6 inches at approximately 85’. All lines are under hydro test; Ok to cover progress areas.
11/19/2025 COT - LCPL - Sewer  Partial Pass Tie into man hole at south end. Tie into main building along with a future 10’ stub out heading east near entry. Okay to backfill all progress areas. Ensure green tape is in place after first lift of compaction. 11/19/2025