Inspection History Details
Inspection Status: Canceled
Inspection History: BULD - Electrical Clearance
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 01/14/2025 | BULD - Electrical Clearance | Canceled | unable to contact contractor | |
| 01/24/2025 | BULD - Electrical Clearance | Re-inspection required | 01/24/25 1. Missing address label. 2. Mast over 3 feet not supported. 3. Missing support on riser, only has one at the moment. |
|
| 02/14/2025 | BULD - Electrical Clearance | Partial Pass | 14 FEB 25 TEP CLEARANCE: INCR partial pass , pending solar. |
|
| 02/28/2025 | BULD - Electrical Clearance | Canceled | ||
| 03/07/2025 | BULD - Electrical Clearance | Passed | 3/7/25 partial pass granted for TEP INCR. pending solar for full clearance. | |
| 04/23/2025 | BULD - Electrical Clearance | Passed | Approved solar - DGC Clearance to TEP is required for the solar meter | |
| 04/23/2025 | BULD - Electrical Clearance | Passed | duplicate | |
| 12/17/2024 | BULD - Electrical Clearance | Not Ready |