Inspection Status: Canceled

Inspection History: BULD - Electrical Clearance

Date Description Inspector Results Comments
10/15/2025 BULD - Electrical Clearance Canceled
10/16/2025 BULD - Electrical Clearance Passed 10.16.2025
Clearance to TEP DGC.
11/10/2025 BULD - Electrical Clearance Passed 11.10.2025
Passed on 10.16.2025 and TEP said waiting on documents from Renewables Department.
12/08/2025 BULD - Electrical Clearance Re-inspection required 12/09/2025
Please upload revised SolarApp checklist to reflect change from piercing connector for line side tap to junction box with 1/0 AWG per latest plans.
12/08/2025 BULD - Electrical Clearance Partial Pass 12/08/2025
TEP needs to verify meter socket adapter or line side tap was performed per TEP technician notes. Assigned inspection for tomorrow.
12/09/2025 BULD - Electrical Clearance Passed 12/09/2025
Approved: Clearance to TEP DGC/DGL. Yesterday had powerkill for DGL line side tap and verified in SolarApp checklist the Polaris connectors in junction box. I field-verified that there was a line-side tap on site and not a meter socket adapter - approved per plan.