Inspection Status: Partial Pass
Inspection History: BULD - Electrical Clearance
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 01/16/2025 | BULD - Electrical Clearance | Partial Pass | Partial for the 200A service panel upgrade - INCR Clearance was called into TEP at 1:30pm Pending solar |
|
| 01/30/2025 | BULD - Electrical Clearance | Re-inspection required | System should have a non fused disconnect, needs revised plans or swapped for non fused disconnect | |
| 02/06/2025 | BULD - Electrical Clearance | Passed | Approved with pics - DGC Clearance to TEP is required for the solar meter | |
| 12/13/2024 | BULD - Electrical Clearance | Canceled | by contractor |