Inspection History Details
Inspection Status: Re-inspection required
Inspection History: BULD - Electrical Clearance
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 12/05/2025 | BULD - Electrical Clearance | Re-inspection required | 12/05/2025 Unable to verify AWG wires size on photos - please upload closeup of wire sizes. SolarApp checklist calls for 21 modules on the roof, but photos are only showing 20 panels laid out differently to plan layout - please verify count and upload photo of all panels or update plans to reflect change in field. |
|
| 12/10/2025 | BULD - Electrical Clearance | Passed | 12/10/2025 Clearance to TEP DGC. Approved per uploaded plans and SolarAPP checklist on 12/04/2025 showing 20 modules on rooftop, verified wire sizes with uploaded photos. |
|
| 12/12/2025 | BULD - Electrical Clearance | Passed | 12/10/2025 Clearance to TEP DGC. Approved again per uploaded plans and SolarAPP checklist showing 20 modules on rooftop, verified wire sizes with uploaded photos. Reviewer has also approved planset. |