Inspection History Details
Inspection Status: Re-inspection required
Inspection History: BULD - Electrical Clearance
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 10/13/2025 | BULD - Electrical Clearance | Re-inspection required | Unable to contact on site electrician | |
| 10/16/2025 | BULD - Electrical Clearance | Partial Pass | 10.16.2025 Clearance to TEP INCR for 200A MPU cutover. Partial pending solar final. |
|
| 11/24/2025 | BULD - Electrical Clearance | Passed | Passed 11/24/25 CLEARANCE DGC/BAT | |
| 11/24/2025 | BULD - Electrical Clearance | Passed | Passed 11/24/25 CLEARANCE DGC/BAT | |
| 11/24/2025 | BULD - Electrical Clearance | Passed | Passed 11/24/25 CLEARANCE DGC/BAT |