Inspection History Details
Inspection Status: Partial Pass
Inspection History: BULD - Electrical Clearance
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 10/15/2025 | BULD - Electrical Clearance | Partial Pass | 10.15.2025 Verbal clearance for TEP INCR at 12pm for 200A MPU. Partial pending solar final. |
|
| 11/03/2025 | BULD - Electrical Clearance | Canceled | 11.3.25 CANCELED PER CONTRACTOR. CONTRACTOR DOES NOT HAVE ACCESS TO EQUIPMENT ON SITE. |
|
| 11/03/2025 | BULD - Electrical Clearance | Canceled | 11.3.25 CANCELED PER CONTRACTOR. CONTRACTOR DOES NOT HAVE ACCESS TO EQUIPMENT ON SITE. |
|
| 11/12/2025 | BULD - Electrical Clearance | Canceled | ||
| 11/12/2025 | BULD - Electrical Clearance | Canceled | ||
| 11/26/2025 | BULD - Electrical Clearance | Passed | Passed 11/26/26 CLEARANCE DGC | |
| 11/26/2025 | BULD - Electrical Clearance | Passed | Passed 11/26/26 CLEARANCE DGC |