Inspection History Details
Inspection Status: Partial Pass
Inspection History: BULD - Electrical Clearance
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 09/25/2025 | BULD - Electrical Clearance | Partial Pass | 9.25.2025 Verbal clearance to TEP INCR at 10:15am. Partial pending solar final. |
|
| 10/09/2025 | BULD - Electrical Clearance | Re-inspection required | 10.09.2025 SolarApp checklist shows combiner panel conductor wire as #4 AWG, but currently #6 AWG is being used and plans show #6 AWG. Please change or revise and upload into the TDC online portal. |
|
| 11/26/2025 | BULD - Electrical Clearance | Passed | 11.26.2025 Clearance to TEP DGC. |