Permit: TC-SOL-0825-01066

Parcel: 131070740


Addresses:

6222 E 24TH ST

Inspection Status: Partial Pass

Inspection History: BULD - Electrical Clearance

Date Description Inspector Results Comments
09/25/2025 BULD - Electrical Clearance Partial Pass 9.25.2025
Verbal clearance to TEP INCR at 10:15am. Partial pending solar final.
10/09/2025 BULD - Electrical Clearance Re-inspection required 10.09.2025
SolarApp checklist shows combiner panel conductor wire as #4 AWG, but currently #6 AWG is being used and plans show #6 AWG. Please change or revise and upload into the TDC online portal.
11/26/2025 BULD - Electrical Clearance Passed 11.26.2025
Clearance to TEP DGC.