Inspection Status: Partial Pass
Inspection History: BULD - Electrical Clearance
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 10/01/2025 | BULD - Electrical Clearance | Partial Pass | Partial for the Tesla switch - DGL Clearance was called into TEP at 10:00 am Pending solar final |
|
| 10/10/2025 | BULD - Electrical Clearance | Canceled | 10.10.2025 Canceled by contractor. |
|