Inspection History Details
Inspection Status: Partial Pass
Inspection History: BULD - Electrical Clearance
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 08/20/2025 | BULD - Electrical Clearance | Partial Pass | Partial for the Tesla switch - DGL Clearance to TEP was called into at 11 am Pending solar final |
|
| 08/28/2025 | BULD - Electrical Clearance | Passed | Approved solar with 2- PW3 - DGC/BAT Clearance to TEP is required for the solar meter |