Inspection History Details
Inspection Status: Not Ready
Inspection History: BULD - Electrical Clearance
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 08/13/2024 | BULD - Electrical Clearance | Not Ready | 8/13/24: not ready | |
| 08/13/2024 | BULD - Electrical Clearance | Partial Pass | Partial for the 125A service panel upgrade - INCR Clearance was called into TEP at 4:25pm Pending solar |
|
| 09/24/2024 | BULD - Electrical Clearance | Canceled | by Contractor | |
| 11/04/2024 | BULD - Electrical Clearance | Partial Pass | Partial for the 200A service panel upgrade - INCR Clearance was called into TEP Pending solar |
|
| 11/13/2024 | BULD - Electrical Clearance | Canceled | Canceled per Juan 11/13/24 | |
| 11/22/2024 | BULD - Electrical Clearance | Passed | Installed per plans, grounding and labeling correct. Passed final 11/22/24 CLEARANCE DGC |