Inspection History Details
Inspection Status: Partial Pass
Inspection History: BULD - Electrical Clearance
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 04/25/2025 | BULD - Electrical Clearance | Partial Pass | Partial for the 125A service panel upgrade - INCR Clearance to TEP is required for the cutover Pending solar |
|
| 08/05/2025 | BULD - Electrical Clearance | Canceled | by contractor | |
| 10/01/2025 | BULD - Electrical Clearance | Not Applicable | ||
| 10/01/2025 | BULD - Electrical Clearance | Passed | Approved solar with PW3 - DGC/BAT Clearance to TEP is required for the solar meter | |
| 10/01/2025 | BULD - Electrical Clearance | Passed | duplicate |