Inspection Status: Partial Pass
Inspection History: COT - RSBU - Masonry Pregrout
| Date |
Description |
Inspector |
Results |
Comments |
| 04/15/2024 |
COT - RSBU - Masonry Pregrout |
|
Partial Pass |
Retaining section, West side and west half of North side. |
| 05/24/2024 |
COT - RSBU - Masonry Pregrout |
|
Passed |
5/24/24: CMU masonry wall is laid up to 8 courses, rebar reinforcement is installed every 32" in CMU cells, and horizontally for top bond beam. Okay to grout cels to the top. |