Inspection History Details
Inspection Status: Re-inspection required
Inspection History: RSBU - Building Final
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 10/31/2025 | RSBU - Building Final | Re-inspection required | 10-31-25: paint all exterior pvs/abs on rooftop, missing mini-split head ( a revision with calculations from architect/engineer is required if you choose to only use one). The mini split is over amped-max breaker is a 15 amp, properly anchor mini split to pad, replace 80 amp main house breaker from main electrical panel to Casita with a 100amp, and wrap hot copper lead of water heater together with pressure relief valve with R-3 insulation. | |
| 11/25/2025 | RSBU - Building Final | Re-inspection required | 10-31-25: paint all exterior pvs/abs on rooftop, missing mini-split head ( a revision with calculations from architect/engineer is required if you choose to only use one). The mini split is over amped-max breaker is a 15 amp, properly anchor mini split to pad, replace 80 amp main house breaker from main electrical panel to Casita with a 100amp. 11.25.25 Mini split still over amped as per previous notes. Properly anchor mini split to slab. |
|
| 12/09/2025 | RSBU - Building Final | Passed |