Inspection Status: Partial Pass
Inspection History: COT - RSBU - Excavation/Rebar/ZoningĀ
| Date |
Description |
Inspector |
Results |
Comments |
| 10/29/2026 |
COT - RSBU - Excavation/Rebar/ZoningĀ |
|
Partial Pass |
#4 reinforcing correct in pier footings to plan and detail. Confirm with engineer that Rebar does not need to be at top and bottom of footer. If so- okay to pour pier footers. the full scope of all the walls are not on plan. Revise and submit the plan for approval showing the retaining wall detail and the location of it on the plan. Schedule pre-grout inspection prior to grouting piers. |