Permit: TC-RES-1025-05079

Parcel: 133220630


Addresses:

7261 E ELBOW BAY PL

Inspection Status: Canceled

Inspection History: COT - RSBU - Residential Intermediate may include Framing, Electrical, Plumbing, HVAC and/or Mechanical work. Only one inspection may be attached for all trades for final rough-in.

Date Description Inspector Results Comments
01/27/2026 COT - RSBU - Residential Intermediate may include Framing, Electrical, Plumbing, HVAC and/or Mechanical work. Only one inspection may be attached for all trades for final rough-in. Canceled
01/27/2026 COT - RSBU - Residential Intermediate may include Framing, Electrical, Plumbing, HVAC and/or Mechanical work. Only one inspection may be attached for all trades for final rough-in. Canceled
02/04/2026 COT - RSBU - Residential Intermediate may include Framing, Electrical, Plumbing, HVAC and/or Mechanical work. Only one inspection may be attached for all trades for final rough-in. Canceled
02/04/2026 COT - RSBU - Residential Intermediate may include Framing, Electrical, Plumbing, HVAC and/or Mechanical work. Only one inspection may be attached for all trades for final rough-in. Canceled Work too incomplete to inspect.
02/05/2026 COT - RSBU - Residential Intermediate may include Framing, Electrical, Plumbing, HVAC and/or Mechanical work. Only one inspection may be attached for all trades for final rough-in. Partial Pass 02/05/2026
Partial pass pending revision/letter uploaded to TDC online portal showing changes and additions to electrical and plumbing plans. DWV not under test. Seal top plate penetrations with fire foam, bottom plates in contact with concrete foundation needs preservative treatment, secure electrical wires 8" from receptacle box, add bracing 33"-36" for grab bars at water closet, add exhaust fan and duct in bathroom. Proceed in progress areas with remaining framing and sealing exterior wall.
02/05/2026 COT - RSBU - Residential Intermediate may include Framing, Electrical, Plumbing, HVAC and/or Mechanical work. Only one inspection may be attached for all trades for final rough-in. Partial Pass 02/05/2026
Partial pass pending revision/letter uploaded to TDC online portal showing changes and additions to electrical and plumbing plans. DWV not under test. Seal top plate penetrations with fire foam, bottom plates in contact with concrete foundation needs preservative treatment, secure electrical wires 8" from receptacle box, add bracing 33"-36" for grab bars at water closet, add exhaust fan and duct in bathroom. Proceed in progress areas with remaining framing and sealing exterior wall. Duplicate.
02/13/2026 COT - RSBU - Residential Intermediate may include Framing, Electrical, Plumbing, HVAC and/or Mechanical work. Only one inspection may be attached for all trades for final rough-in. Partial Pass 2.13.26
Partial pass pending revision submission as noted before.
Blocking for grab bars required at bathroom per previous notes.
Exhaust fan required at bathroom

Ok to cover progress areas, leave noted areas exposed
02/13/2026 COT - RSBU - Residential Intermediate may include Framing, Electrical, Plumbing, HVAC and/or Mechanical work. Only one inspection may be attached for all trades for final rough-in. Partial Pass 2.13.26
Partial pass pending revision submission as noted before.
Blocking for grab bars required at bathroom per previous notes.
Exhaust fan required at bathroom

Ok to cover progress areas, leave noted areas exposed