Inspection History Details
Inspection Status: Partial Pass
Inspection History: BULD - Electrical Clearance
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 01/30/2025 | BULD - Electrical Clearance | Partial Pass | Partial for the 200A service panel upgrade - INCR Clearance was called into TEP Pending solar |
|
| 03/14/2025 | BULD - Electrical Clearance | Passed | Approved solar with powerwall 3 - DGC/BAT Clearance to TEP is required for the solar meter | |
| 12/30/2024 | BULD - Electrical Clearance | Canceled | Canceled per contractor. 12/30/2024 |