Inspection History Details
Inspection Status: Re-inspection required
Inspection History: COT - RSPL - Plumbing Final
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 09/22/2026 | COT - RSPL - Plumbing Final | Re-inspection required | 9/22/26: support booster pump at water heater, insulation required on hot water side of water heater, flexible gas connector for pressure relief valve not allowed, all hot pex lines 3/4" must be properly supported ( cannot lie on trusses) and require insulation, add insulation to hose bib at front yard and seal penetration at exterior wall and provide a ladder for attic access. Reschedule inspection when corrections are made. | |
| 09/28/2026 | COT - RSPL - Plumbing Final | Re-inspection required | 9/28/26: no answer at pre call or at residence. Rang door bell a few times, waited a few minutes and left. Note: a water heater pan is required. I forgot to add to previous notes. |
|
| 09/29/2026 | COT - RSPL - Plumbing Final | Partial Pass | 9/29/26: partial pass pending section of R3 insulation on hot copper line of water heater. Provide a photo so that I may close out permit. | |
| 10/01/2026 | COT - RSPL - Plumbing Final | Passed | 10/1/26: plumbing final approved. |