Inspection History Details
Inspection Status: Not Ready
Inspection History: COT - RSBU - Preslab
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 01/14/2026 | COT - RSBU - Preslab | Not Ready | 1.14.25 Simpson hold downs are not in place. Footers are not clean of loose dirt and debris. Slab area still has large dirt piles and is not compacted. NOT READY. |
|
| 01/16/2026 | COT - RSBU - Preslab | Re-inspection required | 1-16-26: add a #4 at hold-downs and extend 2' out at each end, DWV requires a 1 1/2" clearance from forms, and lift up/re-adjust hold-downs to where bottom holes are flush with top of form. | |
| 01/20/2026 | COT - RSBU - Preslab | Passed | Ensure slab area is termite treated. Ok to place concrete in progress areas, |