Permit: TC-RES-0924-05671

Parcel: Unknown


Addresses:

Inspection Status: Re-inspection required

Inspection History: COT - RSBU - Residential Intermediate may include Framing, Electrical, Plumbing, HVAC and/or Mechanical work. Only one inspection may be attached for all trades for final rough-in.

Date Description Inspector Results Comments
08/01/2025 COT - RSBU - Residential Intermediate may include Framing, Electrical, Plumbing, HVAC and/or Mechanical work. Only one inspection may be attached for all trades for final rough-in. Re-inspection required 8.1.25
Brace 4 slot electrical boxes
DWV not under test
Circuit count does not match plans
STOPPED INSPECTION MORE ITEMS MAY BE PRESENT
08/12/2025 COT - RSBU - Residential Intermediate may include Framing, Electrical, Plumbing, HVAC and/or Mechanical work. Only one inspection may be attached for all trades for final rough-in. Re-inspection required 8.12.2025
Partial corrections made, DWV still not under test, electrical panel A has 15 circuits but plan shows 22, PEX line needs to be 12” from recessed light or blocked, seal exterior penetrations, missing exhaust fan in bathroom, missing some nail plates in ABS in bathroom within 1.5” of stud face, secure ABS at ceiling in bathroom, secure condensate line, secure electrical line set in study. Water heater room required 18” of copper line from main and up to the two PEX lines. Existing house Romex line cannot be in masonry walls, PEX in crawl space needs insulated. Storage area approved.
08/15/2025 COT - RSBU - Residential Intermediate may include Framing, Electrical, Plumbing, HVAC and/or Mechanical work. Only one inspection may be attached for all trades for final rough-in. Passed 8.15.2025
Corrections made, okay to proceed.