Inspection Status: Partial Pass

Inspection History: RSBU - Building Progress

Date Description Inspector Results Comments
01/26/2026 RSBU - Building Progress Partial Pass Inspection call for construction meeting
02/03/2026 RSBU - Building Progress Not Ready Please recall inspection after special inspection is completed
02/18/2026 RSBU - Building Progress Not Ready inspection call for intermediate two window openings. Do not have trimmer king stud arrangement on header properly and opening for slider to backyard needs tohave double king double trimmers. grounds need to be made up on all metal boxes prior to trim.
02/20/2026 RSBU - Building Progress Re-inspection required no current plans on site
02/26/2026 RSBU - Building Progress Partial Pass
03/03/2026 RSBU - Building Progress Passed Inspection call for drywall nailing OK to proceed
12/12/2025 RSBU - Building Progress Not Ready Inspection called for pre-con meeting
12/16/2025 RSBU - Building Progress Partial Pass rough soil leak check good, partial approval for interior post tension repair and ok to place concrete for shower pan. please upload paperwork on portal.
12/19/2025 RSBU - Building Progress Partial Pass partial pass for shower pan