Inspection Status: Re-inspection required

Inspection History: COT - RSPL - Rough Soil 

Date Description Inspector Results Comments
11/25/2025 COT - RSPL - Rough Soil  Re-inspection required 11-25-25: underground plumbing and preslab were called in together. Contractor had already backfilled underground plumbing without an inspection. Therefore, Expose all underground plumbing, extend vent to 10' and fill with water, missing green tracer wire for sewer. DWV cannot be in direct contact with reinforcement- a 1 1/2" clearance is required from reinforcement and forms. Reschedule inspection is required.
11/26/2025 COT - RSPL - Rough Soil  Passed