Inspection Status: Passed
Inspection History: BULD - Electrical Clearance
| Date |
Description |
Inspector |
Results |
Comments |
| 04/09/2024 |
BULD - Electrical Clearance |
|
Passed |
|
| 06/25/2024 |
BULD - Electrical Clearance |
|
Canceled |
Canceled per Karl. |
| 06/27/2024 |
BULD - Electrical Clearance |
|
Canceled |
6/27/24 - CANCELED by inspector - no return communication from contractor after many calls and messages. |
| 10/01/2024 |
BULD - Electrical Clearance |
|
Re-inspection required (with fee) |
|
| 10/08/2024 |
BULD - Electrical Clearance |
|
Re-inspection required |
Failed - work is incomplete, provide approved plans on site and reschedule when complete |
| 12/12/2024 |
BULD - Electrical Clearance |
|
Passed |
Approved with. 60A meter adapter - DGC/DGL Clearance to TEP is required for the solar meter |