Inspection Status: Not Ready
Inspection History: COT - RSBU - Masonry Pregrout
| Date |
Description |
Inspector |
Results |
Comments |
| 04/03/2026 |
COT - RSBU - Masonry Pregrout |
|
Not Ready |
4-3-26: install required reinforcement at existing wall & install new cmu walls up to 4' and schedule an inspection prior to grout. |
| 04/10/2026 |
COT - RSBU - Masonry Pregrout |
|
Partial Pass |
4-10-26: reinforcement at cmu walls approved-Okay to grout 1st lift at 4' 6". |
| 04/14/2026 |
COT - RSBU - Masonry Pregrout |
|
Partial Pass |
04/14/2026: okay to proceed, verified first lift of CMU wall per foundation detail and plan. |
| 04/22/2026 |
COT - RSBU - Masonry Pregrout |
|
Passed |
4/22/2026 final lift approved. Okay to grout all progress areas. |