Inspection Status: Re-inspection required
Inspection History: COT - RSBU - Excavation/Rebar/Zoning
| Date |
Description |
Inspector |
Results |
Comments |
| 03/06/2026 |
COT - RSBU - Excavation/Rebar/Zoning |
|
Re-inspection required |
3-6-26: schedule an underground plumbing inspection. Uncover/expose all underground plumbing so that we may verify that it was install per approved plans and have system under test. Reschedule at your convenience. |
| 03/10/2026 |
COT - RSBU - Excavation/Rebar/Zoning |
|
Partial Pass |
3/10/26: Reinforcement per approved plans at footing. Please backfill trench and compact then call inspection for Preslab |
| 03/20/2026 |
COT - RSBU - Excavation/Rebar/Zoning |
|
Partial Pass |
3/20/26: Preslab approved ok to proceed with concrete placement. |
| 04/10/2026 |
COT - RSBU - Excavation/Rebar/Zoning |
|
Partial Pass |
4-10-26: reinforcement at cmu walls approved-Okay to grout 1st lift at 4' 6". |
| 04/14/2026 |
COT - RSBU - Excavation/Rebar/Zoning |
|
Partial Pass |
04/14/2026: okay to proceed, verified first lift of CMU wall per foundation detail and plan. |
| 04/22/2026 |
COT - RSBU - Excavation/Rebar/Zoning |
|
Passed |
|