Inspection Status: Partial Pass
Inspection History: BULD - Electrical Clearance
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 02/19/2025 | BULD - Electrical Clearance | Partial Pass | Partial for the 125A service panel upgrade, INCR Clearance was called into TEP at 12:05pm Pending solar |
|
| 02/21/2025 | BULD - Electrical Clearance | Passed | Approved - DGC clearance to TEP is required for the solar meter | |
| 12/03/2024 | BULD - Electrical Clearance | Re-inspection required | I could not get in contract with the contractor or owner. 12/2/24 |